90-day moratorium adopted
The BOCC adopted a 90-day moratorium by motion, 3–2, covering Project Bluestem and other data-center, battery-storage, and crypto-related proposals while regulations and additional information were considered.
A source-grounded record of Leavenworth County's data-center debate: what has been formally decided, what County consultants modeled, what residents and officials have said, and what remains unverified in the publicly posted record.
Official actions and primary documents are separated from consultant projections, representations attributed to project or utility parties, public testimony, and information that is not yet established in the public record. A claim being discussed at a public meeting does not automatically make the underlying claim true.

The sequence below uses official minutes, official recordings, Planning Commission packets, moratorium drafts, and County consultant materials. Where a document is missing, the limitation is stated. Click any event for evidence details.
The BOCC adopted a 90-day moratorium by motion, 3–2, covering Project Bluestem and other data-center, battery-storage, and crypto-related proposals while regulations and additional information were considered.
BOCC materials included a revised data-center regulation draft and separate draft moratoria. Official minutes show no action on those separate June moratorium drafts.
The Planning Commission worked through data-center and BESS standards including zoning pathways, development agreements, closed-loop cooling, setbacks, public sound monitoring, third-party inspections, and developer-funded improvements.
County records show authorization of Kutak Rock for legal services related to the proposed data-center development, with cost to be paid from Cloverleaf-provided funds. The executed engagement agreement was not publicly located.
A motion to extend the data-center moratorium through January 31 failed. County staff then indicated the existing moratorium would expire.
At the public hearing, the Planning Commission tabled the proposed language amendments until the next month's meeting and requested a joint BOCC/Planning Commission work session. Andrew Gribble cast the no vote. Staff also stated there was no formal data-center application before the Commission that night.
The next day's official BOCC recording states that a project proposal had “came forward yesterday.” The public archive review did not locate the date-stamped application package or a public case number.
Unsigned draft Resolution 2026-14 was in the packet. During the official recording, County officials said the new filing changed the legal posture, and the Board tabled the moratorium item. The draft Aug. 19 minutes later embedded in the Aug. 26 packet omit this discussion.
This is the site's central distinction. Each category has a different evidentiary weight.
That distinction is essential. Project-related governmental costs were not quantified in the report, and several major inputs remain assumptions or were supported by underlying materials that were not publicly posted.
The County's public record shows a mechanism for the developer side to fund County third-party work. The posted agreement itself is unsigned and undated, so this site distinguishes the posted instrument from proof of execution.
The publicly posted agreement names Western Meadowlark ProjectCo LLC and Leavenworth County, establishes an initial $450,000 fund for eligible third-party expenses, and caps aggregate contributions at $500,000 without developer consent.
County records later show Kutak Rock authorization for specialized legal work and an SMH roadway-engineering proposal. The record should be read as County-retained professional work paid from developer-provided funds — not as proof that those professionals represented the developer.
The archive preserves four distinct versions and the Planning Commission's August decision not to advance the latest draft yet.
| Version | Status | What it shows |
|---|---|---|
| April 29 / May 6 | Found | Early BOCC regulatory draft and initial framework. |
| June 10 | Found | Revised BOCC work-session draft; included an 85 dBA property-line figure with tonal reduction language. |
| July 8 | Found | Planning Commission work-session draft and detailed discussion; commissioners moved toward 65 dBA, reduced to 55 dBA with tonal presence. |
| August 12 — DEV-26-100 | Found | Public-hearing draft; Planning Commission tabled it 8–1 for additional work. |
| Post-August 12 revision | Not publicly located | No later revised draft was found in the reviewed County packets through the archive cutoff. |
The August draft contains more explicit lifecycle protections for battery energy storage systems than for data centers. Staff explained that the regulatory pathways differ; critics argued comparable protections should be applied to the larger use.
The data-center framework relies more heavily on rezoning/development-plan review and project-specific development agreements for performance standards, penalties, and site-specific conditions.
Important: “Permitted by right” in a PIT district does not mean permitted anywhere in the County without review. The land would first have to obtain the applicable zoning and proceed through the required development-plan/public process.
These are not accusations or assumptions. They are simply matters that the publicly posted materials reviewed through August 25 do not establish.
The public record is already sufficient to document the County's formal actions, the regulatory timeline, consultant analyses, funding structure, and the limits of what has been publicly posted. Missing documents are identified as missing rather than filled in with assumptions. That makes the record useful now while remaining updateable as new official material is posted.
The Source Library organizes the official BOCC and Planning Commission recordings, meeting packets, minutes, regulation drafts, consultant work, and source-gap notes used for this page.